The Federal government through the Growing Regions Round 2 program has provided the Shire with $13.4 million that will be used to replace the Wyndham Community Boat Launching Facility to make it safer and more accessible for users, and to improve amenities and enhance liveability and recreational opportunities.
News feed
Timeline
-
Timeline item 1 - active
Contractors mobilisation site
- Contractor mobilisation and site establishment commenced.
- Piles were delivered to site.
- Pontoon manufacturing is underway and progressing well.
-
Timeline item 2 - incomplete
Construction Commences
Contractor is scheduled to commence construction on 19 May, including driving the first two piles from land.
Further updates regarding any potential disruptions will be provided as works progress.
-
Timeline item 3 - incomplete
Construction Complete