Progress Update: April 2025
The Detailed Design and Costing phase for the Barytes Road Realignment project is set to be completed this month, marking a key milestone in progressing this important project.
Following completion, the Shire will enter discussions with Main Roads WA to plan for project delivery within the year.
This construction phase will also serve as a valuable opportunity to upskill Shire staff in road construction, supporting our goal of building internal capacity to deliver similar works in the future.
Share Progress Update: April 2025 on Facebook
Share Progress Update: April 2025 on Twitter
Share Progress Update: April 2025 on Linkedin
Email Progress Update: April 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends